Read moreClient: Aiken ECI
List of Completed Projects:
| Project/Contact | Tasks | Project Management |
North 115/12 kV Substation Terry Walker |
Engineered modification by retiring existing 69/12 kV station with new 115/12 kV transformer, circuit switcher and six feeder bays with reclosers. |
Physical, Relay and Control Design, RUS spec and contract. Secured material through construction contractor. Secured Control House through packagers, managed construction, and commissioned the station and closed all the RUS documents. |
Sage Mill 115/12 kV Substation Terry Walker |
Engineered new 115/12 kV station with transformer, circuit switcher and six feeder bays with reclosers. |
Physical, Relay and Control Design, RUS spec and contract. Secured material through construction contractor. Secured Control House through packagers, managed construction, and commissioned the station and closed all the RUS documents. |
Bealieu 115/12 kV Substation Terry Walker |
Engineered modification of adding two 115/12 kV transformers, circuit switchers and four feeder breakers in an existing 115/12 kV station. |
Physical, Relay and Control Design, RUS spec and contract. Secured material through construction contractor. Secured Control House through packagers, managed construction, and commissioned the station and closed all the RUS documents. |
Eureka 115/12 kV Substation Terry Walker |
Engineered new 115/12 kV station with transformer, circuit switcher, and six feeder bays with reclosers. |
Physical, Relay and Control Design, RUS spec and contract. Secured material through construction contractor. Secured Control House through packagers, managed construction, and commissioned the station and closed all the RUS documents. |
Windsor 115/25 kV Substation Terry Walker |
Engineered modification by retiring existing 115/12 kV station with new 115/25 kV transformer, circuit switcher and six feeder bays with reclosers. |
Physical, Relay and Control Design, RUS spec and contract. Secured material through construction contractor. Secured Control House through packagers, managed construction, and commissioned the station and closed all the RUS documents. |